See a workbench on work you'll recognize.
Pick a workflow. You'll see a normal day today, the same day in the workbench, and what changes.
Demo · Production & Delivery Risk Workbench
Know which committed orders won't ship on time, while there's still time to fix it.
Recognize this? Whether a batch can run depends on six places.
Wednesday, Oct 21. Luis Ortega plans production at a specialty chemicals plant. Next week has 14 batches. This is one of them.
Where the AD-310 batch lives this morning
- Supplier emailNorchem: "IPDI delivery moves from Mon Oct 26 to Wed Oct 28." Sent to the buyer.
- ERPPO 7731 still expects IPDI Monday
- Schedule sheetAD-310 for Pinecrest on Reactor R-1, Monday 8 AM
- InventoryNot enough IPDI on hand for one batch
- Sales orderPinecrest SO-4490 ships Oct 30
- MaintenanceReactor R-2 down Tuesday
What it takes Luis to find out
- 0:00Open the schedule spreadsheet
- 0:06Check inventory for each batch's inputs
- 0:15Ask purchasing whether anything is late
- 0:15–0:40Wait for the buyer to reply
- 0:40Buyer forwards Norchem's email
- 0:48Work out which batches use IPDI and what else could run
50 minutes to check one week. And only if someone asks.
And it gets harder. Usually nobody asks. The plant finds out Monday at 6 AM when the IPDI isn't there, and Reactor R-1 sits idle while the planner reshuffles.
Production & Delivery Risk Workbench
Know which committed orders won't ship on time, while there's still time to fix it.
What it connects
- Supplier and purchasing email
- ERP purchase orders and inventory
- Recipes or bills of materials
- Production schedule and capacity
- Committed sales orders
What closes an issue
- Delivery confirmed in writing
- Schedule and ERP updated
- IPDI received
- AD-310 shipped Oct 30
Why not a planning or scheduling tool?
A scheduling tool optimizes the plan it's given. It doesn't read the supplier's email that changed it. The workbench catches the change, shows what it breaks and proposes the fix for the planner to approve.
Open any item
Every item carries its evidence, from the first signal to the close.
What changed, why it matters, what's known and from where, what's still uncertain, what happens next and who approved it, and what closed it.
In Workbench Starter: built from one person's email and the exports they add.
In the Operations Workbench: built from live ERP and planning data, for the whole team, with approvals and write-back.
PO 4512 · Machined housings · Ridgeway Machining
Closed · verifiedWhat changed
- Delivery dateOct 12 → Oct 26Ridgeway email, Oct 5
Why it matters
- Assembly run A-88Needs the housings Oct 20Production schedule
- Brightline · ships Oct 28$138,000Committed orders
- Keller · ships Nov 2$76,000Committed orders
What we know
- New date Oct 26, tooling issue on line 2ConfirmedSupplier email · Oct 5, 7:48 AM
- ERP still shows Oct 12ConflictsOpen-PO export · loaded Oct 4
- Ridgeway slipped twice this year, ~11 days eachPatternItem history
What's still uncertain
- Whether Ridgeway can split the shipmentAsked Oct 5No reply yet
What happens next
- Ask Ridgeway to split: 60 housings by Oct 19, the rest Oct 26Owner: Maya OrtizApproved Oct 5, 9:12 AM
What closed it
- Split confirmed in writingRidgeway email · Oct 7✓
- 60 housings received for run A-88Receipt in PO export · Oct 19✓
Illustrative mockup · sample company and data